Tentative Work Schedule

September 17, 2018

 

Work in the NW section consists of Grading NW 188th, NW 71st, 193rd, Dig ditch on NW 53rd Ave. and Trim Market Road

 

Work in the SE section consists of Re-working SE 71st, SE 72nd and 73rd, Install culvert on 273 SE 59th St., Dig ditch and Blow out on SE CR 18 starting at SE 43rd and clean out & Trim concrete ditches on SE 4th

 

Work in the SW section consists of Finishing culvert on SW 106th

 

 

We received 3 DOC Squads for a total of 17 people

 

1 Squad will be Cleaning out and trimming up Concrete ditches on SE 4th

 

1 Squad will be Cutting and Trimming Market Road

 

1 Squad will be assisting with traffic control finishing culvert on SW 106th, Installing a culvert on SE 59th St. and Digging ditches on SE CR 18 starting at SE 43rd