Tentative Work Schedule

April 20, 2022

 

Work in the NE section consists of Opening up Culverts on NE 185th St. and Patching Pot Holes on SE 24th Pl.

 

Work in the NW section consists of Grading NW 35th, NW 41st, NW 209th, NW NW 219th St. off NW CR 225 and NW 212th St., and Finish repairing Crossover pipe on NW CR 235 and Patch Pot Holes on NW 214th St.

 

Work in the SE section consists of Grading rods off of SE 57th St. and Crystal Lake Homesites and Mow SE CR 100A

 

Work in the SW section consists of Mowing Sprayfield Road (Braham Lane)

 

Pick up Mattresses, lumber and Household items that was thrown out on NW 71st St.

 

 

We received 2 DOC Officers an no Inmates.  The Inmates were in Lock Down again today. 

)