Tentative Work Schedule

August 4, 2021

 

Work in the NW section consists of Grading NW 38th Ave. and Mowing ROW on NW 180th St.

 

Work in the SE section consists of Grading roads in Crystal Lake Homesites

 

Work in the SW section consists of Grading SW 106th Ave., Adding milling and Spreading on both ends of SW 209th St., Mowing SW CR 235, SW 161st St. and SW CR 231 and using Zero Turn to Mow around Mail boxes, Culverts, Bridges and Guardrails

 

 

We received 2 DOC (BCSO-JAIL) with a total of 6 Inmates

 

1 Squad with 3 Inmates will be Weed eating around Guardrails on SW 161st St.

 

1 Squad with 3 Inmates will be Picking up trash on SW CR 235 and SW 161st St.