Tentative Work Schedule

March 6, 2024

 

Work in the NE section consists of Grading NE 173rd St., NE 19th Lane, NE 12th Ave. and NE 171st St.

 

Work in the NW section consists of Grading NW 44th Ave., NW 74th Ave. and NW 71st Ave., Prepping for Paving and Digging Ditches and Hauling off Dirt on NW 38th Ave. and Mowing the Shoulders of the road on on NW 41st Ave.

 

Work in the SE section consists of Patching Pot Holes on SE CR 214 and Mowing SE 8th Ave. with the Zero Turn

 

Work in the SW section consists of Grading SW 132nd Ave. and Picking up Debris on SW CR 225 

 

 

We received 2 DOC (BCSO-JAIL) Officers and 2 Inmates

 

1 Officer will be assisting in Maintenance

 

1 Officer and 2 Inmates will be Picking up Trash on NW CR 125 and NW CR 225A