Tentative Work Schedule

July 9, 2020

 

Work in the NE section consists of Patching Pot Holes on NE 10th Ave. and Mowing side walk on NE CR 225 with Zero Turn

 

Work in the NW section consists of Grading NW 53rd St. and NW 50th Ave.

 

Work in the SE section consists of Mowing SE 21st Ave., SE CR 100A and SE 144th St.

 

Work in the SW section consists of Grading SW 64th, SW 65th and SW 66th and Trimming ROW on SW CR 237

 

 

We received 2 DOC Squads for a total of 9 people

 

1 Squad will be Picking up trash and Weed eating on SW CR 18

 

1 Squad will be Picking up trash and Weed eating on SE 144th St and SE 150th St.