Tentative Work Schedule

 

 

July 12, 2018

 

Work in the NW section consists of Pulling ditches on NW 205th, Digging a ditch on NW CR 125, Mow with the Side Arm NW 180th St. and Install culverts at 22668 NW 41st Ave.

 

Work in the SW section consists of filling in holes and Grading on SW 206th and Patching pot holes and troughs on SW CR 235.

 

 

We received 3 DOC Squads for a total of 16 people

 

1 Squad will be patching pot holes and troughs on SW CR 235

 

1 Squad will be Picking up trash and weed eating on NW CR 125

 

1 Squad will be conducting traffic for Installing culverts