Tentative Work Schedule

August 30, 2018

 

Work in the NE section consists of Trimming and Chipping around the R/R tracks on NE 204th

 

Work in the NW section consists of Limerocking NW 105th, Replacing Crossover pipe on NW 71st, Pulling ditches on NW 74th Ave. and Patching pot holes on NW 45th and 199th

 

Work in the SW section consists of Grading, Replacing the culvert at 11569 SW 157th Ave. and Hauling 2 loads of dirt to Sampson City Fire Department

 

 

We received 3 DOC Squads for a total of 13 people

 

1 Squad will be patching pot holes on NW 45th and NW 199th

 

1 Squad will be Trimming and Chipping around R/R tracks on NE 204th 

 

1 Squad will be performing traffic control for replacing the culvert at 11569 SW 157th Ave. and Replacing Crossover pipe on NW 71st