Tentative Work Schedule

December 19, 2023

 

Work in the NE section consists of Grading roads in this section

 

Work in the NW section consists of Hauling and Spreading Limerock and Grading NW 71st Ave. and Grading roads in this section

 

Work in the SE section consists of Hauling and Spreading Limerock on SE 66th St. and Grading roads in this section

 

Work in the SW section consists of Grading SW 163rd St.

 

We will also be Hauling Dirt from Market Road Pit to New River Landfill

 

 

We received 2 DOC (BCSO-JAIL) Officers and 2 Inmates 

 

1 Officer will be working with the new Maintenance Director

 

1 Officer and 2 Inmates will be Picking up Trash and Weed Eating SW 180th Ave.