Tentative Work Schedule

August 29, 2018

 

 

Work int he NE section consists of Trimming and Chipping around R/R tracks on NE 204th

 

Work in the NW section consists of Building up and limerocking NW 105th, Pulling ditches on NW 74th Ave., Digging a ditch on NW 53rd Ave. and Mowing with the Side Arm Mower on NW 185th 

 

Work in the SE section consists of Patching pot holes in Keystone Golf and Country Club, Mowing SE CR 100A, Vystar Road and Edwards Road

 

Work in the SW section consists of Slope a ditch on SW CR 225A, Mow SW 66th (Crosby Lake) with the Side Arm Mower and Grade roads off of SW CR 18

 

 

We received 3 DOC Squads for a total of 16 people

 

1 Squad will be patching pot holes in Keystone Golf & Country Club

 

1 Squad will be Trimming & Chipping trees around R/R tracks on NE 204th

 

1 Squad will be directing traffic on SW CR 225A to Slope ditch