Tentative Work Schedule

February 27, 2023

 

Work in the NEW Section consists of Grading NE 17th Ave.

 

Work in the NW section consists of Grading NW 251st and Dig out Side Pipes on NW CR 225

 

Work in the SE section consists of Grading SE 38th, Prep site for Driveway Culvert by Santa FE Boat Ramp and Clean out Ditches and Side Pipes on SE 21st Ave.

 

Work in the SW section consists of Grading SW 114th, SW 180th Ave. and SW 180th Pl. and Building pad for Weighing Trucks on SW CR 235

 

 

We received 1 DOC Officer (BCSO-JAIL) and 3 Inmates.  They will be Cleaning out an Office in the back for the Sign Shop