Tentative Work Schedule

June 26, 2024

 

Work in the NE section consists of Hauling Limerock and Prepping NE 17th to be Chip Sealed

 

Work in the NW section consists of Mowing the Shoulders of the road on NW 105th Ave. and Mowing NW CR 229A and NW CR 233

 

Work in the SE section consists of Mowing the Surplus Property

 

Work in the SW section consists of Grading and Pulling the Ditches on SW 160th and MOT on SW CR 227 for Removing a tree

 

We did not get any Inmates today