Tentative Work Schedule

February 3, 2020

 

Work in the NE section consists of Grading out the ditch on the New Road and checking to be sure it has the flow it needs

 

Work in the NW section consists of Grading off of NW CR 125, Patching driveways on NW CR 125 and Mowing and cleaning high spots an outfall ditch on NW 119th

 

Work in the SW section consists of Working on SW 101st Ave. and prepping for Fog Seal

 

 

We received 3 DOC Squads for a total of 12 people

 

1 Squad will be directing traffic for work being done on SW 101st Ave

 

1 Squad will be Picking up trash on SE 11th Ave. and then on SE CR 18 from SR 100 towards Hampton

 

1 Squad will be putting Grass Seed out on NE 15th Pl.