Tentative Work Schedule

January 30, 2019

 

Work in the NE section consists of Filling in holes and Grade NE 187th St. and Cutting and trimming NE 6th Ave. and NE 227th  (Carter Road)

 

Work in the NW section consists of Grading NW 74th and Digging Ditches on NW CR 235

 

Work in the SW section consists of Grading SW 155th and SW 136th, Opening culvert at the Brooker Collection Site and Replaces Guardrail on SW 163rd St.

 

 

We received 3 DOC Squads for a total of 15 people

 

1 Squad will be Replacing Guardrail on SW 163rd St.

 

1 Squad will be Picking up trash and weed eating on NW CR 229

 

1 Squad will be directing traffic for opening up culvert at the Brooker Collection Site and Digging Ditched on NW CR 235