Tentative Work Schedule

October 18, 2018

Work in the NE section consists of Grading NE 247th 

 

Work in the NW section consists of Pulling ditches on NW 75th Ave., Scooping ditches on NW 84th Ave., Reset the culvert on NW 45th and Install 2 culverts on NW CR 229, Mow NW CR 229, Patch Pot Holes  on NW 44th Ave. and Grade the dirt portion of NW 251st

 

Work in the SE section consists of Patching Pot Holes on SE CR 100A just before the 1st set of R/R tracks and Trimming limbs on SE 8th Ave.

 

Work in the SW section consists of Zipping SW 101st Ave. and Trimming limbs on SW 66th Ave. and Mowing SW 101st Ave. with the Side Arm Mower

 

We received 3 DOC Squads for a total of 16 people

 

1 Squad will be Trimming limbs on SW 66th Ave. and SE 8th Ave.

 

1 Squad will be Mowing and weed eating on NW 37th Ave. off of NW CR 233 (Morgan Road)

 

1 Squad will be directing traffic for Scooping ditches on NW 84th Ave.