Tentative Work Schedule

June 27, 2019

 

Work in the NE section consists of Patch pot holes NE 10th Ave. and NE 219th St. and Grading NE 204th & NE 173rd

 

Work in the SE section consists of Grading SE 50th, 7th, 94th, and down SR 100, SE 87th and off of CR 18, Install culverts on SE 17th Ave. and SE 48th Ave, and Mow SE CR 21B

 

Work in the SW section consists of Cleaning out a box culvert on SW CR 231 (Dedan Loop)

 

 

We received 3 DOC Squads for a total of 13 people

 

1 Squad will be picking up trash and weed eating SE CR 21B

 

1 Squad will be picking up trash and weed eating SE CR 214

 

1 Squad will be directing traffic for installing culverts on SE 17th Ave. & SE 48th Ave.