Tentative Work Schedule

April 17, 2019

 

Work in the NW section consists of Zipping and Packing NW 177th St., Grade NW 41st, NW 209th, NW 35th, Install a culvert at 4037 NW 219th St., Mow NW 22nd Ave. & NW 251st St and Chip debris at NW 53rd Ave. Ditch

 

Work in the SE section consists of Installing a culvert on SE 144th and Cleaning out the Ditch on SE 23rd Ave.

 

Work in the SW section consists of Grading SW 160th, SW 155th, SW 144th, SW 168th & SW 137th

 

 

We received 2 DOC Squads for a total of 8  people

 

1 Squad will be Laying Sod and Chipping debris on NW 53rd Ave. ditch

 

1 Squad will be directing traffic for Installing culverts on SE 144th and at 4037 NW 219th St.