Tentative Work Schedule

November 7, 2018

 

Work in the NE section consists of Pulling ditches on NE 171st, NE 12th and NE 173rd

 

Work in the NW section consists of Grading NW 51st Ave., NW 49th Pl. and NW 219th and Installing Culverts on NW 221st Way

 

Work in the SE section consists of Installing a Culvert on SE 129th St., Mowing off Immokalee Road with the Side Arm and Patching a driveway on SE 66th St.

 

Work in the SW section consists of Zipping SW 101st Ave. and Mowing SW CR 235 and SW CR 231

 

 

We received 3 DOC Squads for a total of 18 people

 

1 Squad will be Picking up trash on SE 21st Ave.

 

1 Squad will be Patching a driveway on SE 66th St

 

1 Squad will be Trimming and Chipping SE 16th St.