Tentative Work Schedule

September 20, 2022

 

Work in the NE section consists of Grading NE 20th Ln. and Ditch work on Carter Road

 

Work in the NW section consists of Grading NW 205th and Mowing ROW on NW 188th St.

 

Work in the SE section consists of Mowing SE CR 18

 

Work in the SW section consists of Grading SW 163rd and SW 676th and Mowing SW 75th Ave., SW CR 100A and SW CR 18

 

 

We received 2 DOC (BCSO-JAIL) Officers and 4 Inmates.  They will be Weed Eating NW CR 233