Tentative Work Schedule

October 3, 2019

 

Work in the NE section Digging the ditch on NE 21st Lane and Mowing NE 19th, NE 17th, NE 28th, NE 173rd and Starke Golf and Country Club

 

Work in the NW section consists of Grading Olin's Mobile Home Park, Off of NW CR 233 and NW 77th Pl., Mowing NW 223rd St., NW 53rd, NW 219th & NW 44th and Patch Pot Holes on NW 45th (Off NW CR 233)

 

Work in the SE section consists of Grading SE 73rd, SE 72nd, SE 71st and down SE CR 18 toward 301, Mow SE 144th (Vystar Road), SE CR 230A, SE 150th St. and Build Walking Path at Lincoln City Park

 

Work in the SW section consists of Grading SW 101st and SW 163rd and adding Concrete bags to Hampton Boat Ramp

 

 

We received 2 DOC Squads for a total of 11 people

 

1 Squad will be Cleaning Equipment to go to Touch A Truck on 10/5/19

 

1 Squad will be Directing traffic and assisting with placing concrete bags around ramp and Digging the ditch on NE 21st Lane

 

BC Jail Officer off today - No Crew