Tentative Work Schedule

March 21, 2019

 

Work in the NE section consists of Patching a driveway at 2170 NE 204th St.

 

Work in the NW section consists of Digging the ditch on NW 53rd Ave. and Install 20780 NW 71st Ave.

 

Work in the SE section consists of Grading SE 49th & SE 86th and Patching driveways on SE 109th & at 3370 SE 136th St.

 

Work in the SW section consists of Grading SW 155th Ave. & SW 136th, Patching Troughs/Shoulders on SW CR 18 and Installing a culvert at 20780 NW 71st Ave and Digging the ditches

 

 

We received 3 DOC Squads for a total of 14 people

 

1 Squad will be Patching driveways

 

1 Squad will be Picking up trash and Weed Eating on NW 71st Ave. between NW 180th & NW CR 229

 

1 Squad will be handling traffic control for installing a culvert at 20780 NW 71st Ave. and Digging Ditches