Work Schedule

 

 

Work in the NW section consists of Grading and Installing a culvert

 

Work in the SE consists of Zipping a road

 

Work in  the SW consists of Milling a road and Patching troughs

 

 

We received 2 DOC Squads for a total of 9 people

 

1 Squad will continue to place silk screen in the SW section and clean out & weed eat ditch at Pine Forest Apts.

 

1 Squad will assist with traffic installing a culvert in the NW section

 

 

1 Squad from The Transition House (4 people) will assist in patching troughs in the SW section