Tentative Work Schedule

August 2, 2022

 

Work in the NW section consists of Grading NW 77th Pl., Picking up Tree debris on NW 124th Ave. and NW 267th St. and Patching holes around the bridge on NW 74th Ave.

 

Work in the SE section consists of Grading SE 49th Ave., SE 75th St. and SE 94th St., Cleaning out the ditches on SE 125th Ter., Mowing ROW on SE CR 221, Mowing SE CR 21B and SE CR 214 and Patching Pot Holes on SE 150th St.

 

Work in the SW section consists of Picking up Tree debris on SW 206th Ave., SW 194th Ave. and SW 161st St.

 

 

We received 1 DOC (BCSO-JAIL) Officer and 4 Inmates and they will be Weed eating on NW 36th Ave.