Tentative Work Schedule

March 4, 2019

 

Work in the NE section consists of Cleaning out ditches on NE 15th Ave.

 

Work in the NW section consists of Cleaning out culverts on NW CR 125

 

Work in the SE section consists of Straightening the ditch where the loader got stuck on SE CR 18, Adding limerock to SE 40th Pl. driveway, Patching pot holes on SE 44th and Filling in troughs on SE CR 21B

 

Work in the SW section consists of Grading SW 101st Ave., Hard Blading  SW 160th (Train Simmie on the Grader) and Patching pot holes on SW CR 235

 

 

We received 3 DOC Squads for a total of 16 people.

 

1 Squad will be Picking up Trash and Weed Eating SW CR 225 and SW CR 227 toward Brooker

 

1 Squad will be Patching a driveway on SE 40th Pl., and Patching pot holes on SE 44th and SW CR 235

 

1  Squad will be straightening out ditch where loader was stuck, Clean out culverts and ditch work on NW CR 125 and Ditch work on NE 15th Ave.