Tentative Work Schedule

August 24, 2020

 

Work in the NW section consists of Grading NW 237th St., Patching Pot Holes and driveways on NW 177th St. and Mowing NW CR 233, NW 216th St., NW CR 229A, Cut ROW and around bridges on NW CR 235, NW CR 225 and on NW 216th St. an d Cleaning out ditches on NW 237th St. (Stop Camp Road)

 

Work in the SE section consists of Patching Pot Holes and driveways on SE 30th St. and Cleaning out the ditches on SE 129th St.

 

Work in the SW section consists of Prepping SW 106th Ave. and Cleaning out ditches on SW CR 235                                                                

 

 

We received 2 DOC Squads for a total of 10 people

 

1 Squad will be Picking up trash and weed eating on NW CR 225

 

1 Squad will be Picking up trash and weed eating the Market Road pit

 

1 County Officer and 2 Temporary Laborers will be Mowing and weed eating around the Shop