Tentative Work Schedule

December 16, 2019

 

Work in the NE section consists of Grading NW 171st St. (Dirt part), NE 173rd St., NE 12th Ave., NE 21st Ln. and NE 19th Ln.

 

Work in the SE section consists of Grading SE 50th (off SE CR 21B by the lake), Crystal Lake Homesites and off SE CR 18

 

Work in the SW section consists of Shoulder work on SW CR 235, Mowing SW 101st Ave. and Patching troughs on SW CR 231

 

 

We received 2 DOC Squads for a total of 9 people

 

1 Squad will be directing traffic and assisting with Patching troughs on SW CR 231

 

1 Squad will be directing traffic and assisting with Shoulder work on SW CR 235