Tentative Work Schedule

August 19, 2019

 

Work in the NE section consists of Grading & Packing NE 20th Lane & NE 204th St., Installing a culvert on NE CR 200B (Peetsville Cemetery), Patching driveway at 893 NE CR 125 and Mowing NE CR 200B, NE 216th St. and NE CR 225

 

Work in the NW section consists of Grading NW 41st Ave., Finish installing culvert on NW CR 225 and Install culvert at (Peetsville) NE CR 200B, Patching driveways on NW CR 225 & NW 35th Ave. and Mow NW 62nd Ave. & NW 214th and NW CR 200A

 

Work in the SE section consists of Cutting up a big tree and hauling it away on SE CR 18

 

Work in the SW section consists of Grading SW 179th St. & SW 132nd Ave.

 

 

We received 3 DOC Squads for a total 17 people

 

1 Squad will be Cutting up and Hauling off a big tree on SE CR 18

 

1 Squad will be Picking up trash on NW CR 229 & NW 216th St.

 

1 Squad will be finishing the installation of culvert on NW CR 225 and install culvert on NE CR 200B (Peetsville Cemetery)