Tentative Work Schedule

July 28, 2020

 

Work in the NW section consists of Mowing NW CR 225A and NW CR 225

 

Work in the SE section consists of Grading Off Fellow Cemetery Road (SE 44th Ave) and Roads off of SE 21st Ave., Mill and Spray ditch on SE 71st St. and  Mow Outfall Ditch on SE 109th St.

 

Work in the SW section consists of Grading SW 101st Ave. from SW CR 225 to SW 163rd (Cypress Run Road) and Prepping SW 106th Ave. for Fog Sealing

 

 

We received 2 DOC Squads for a total of 12 people

 

1 Squad will be Mowing and weed eating Dedan Loop Cemetery

 

1 Squad will be Picking up trash and weed eating SE CR 21B and SE 8th Ave.

 

County Officer will be Mowing Dedan Loop Cemetery with a Zero Turn