Tentative Work Schedule

October 22, 2019

 

Work in the NW section consists of Grading NW 219th (off NW CR 226), NW 251st, NW 238th,NW 25th and down NW CR 125 and Digging Outfall Ditch on NW CR 225

 

Work in the SE section consists of Grading SE 17th Ave., SE 66th (Rock part), SE 86th, SE 49th, SE 46th, SE 106th, SE 101st and down SE CR 18 and Building a parking pad at the Keystone Fire Department

 

Work in the SW section consists of Scooping out concrete ditch on SW 161st St and Mowing SW CR 235, SW 161st St. and SW CR 231

 

 

We received 2 DOC Squads for a total of 8 people

 

1 Squad will be Digging out the ditch pavers on SW 161st St.

 

1 Squad will be directing traffic and assisting with Scooping out concrete ditch on SW 161st St.