Work Schedule

 

Work in the NE section consists of Grading

 

Work in the NW section consists of Grading, Pulling ditches, Cutting, Trimming and Chipping

 

Work in the SE section consists of Zipping a road and Patching pot holes

 

Work in the SW section consists of Grading and Installing a culvert

 

 

We received 2 DOC Squads for a total of 10 people

 

1 Squad will be assisting in Cutting, Trimming and Chipping in the NW section

 

1 Squad will be assisting installing a Crossover culvert in the SW section

 

 

1 Squad from The Transition House (4 people) will be patching pot holes