Tentative Work Schedule

July 15, 2019

 

Work in the NE section consists of Mowing NE 204th St. & NE 20th Ln., Digging the outfall ditch on NE 227th St. and Mowing  NE 173rd St., NE 19th Ave & NE 28th Ave. with Zero turns

 

Work in the NW section consists of Zipping, Packing & Grading NW 37th Ave., Grade NW 84th, limerock part of NW 71st and NW 75th

 

Work in the SE section consists of Mowing SE CR 21B, Cut up, Load & Haul off tree on SE CR 21B and Patch Pot Holes on SE 52nd St.

 

Work in the SW section consists of Grading SW 160th & SW 168th and Installing 3 culverts on SW 80th Pl.

 

 

We received 3 DOC Squads for a total of 13 people

 

1 Squad will be Picking up trash on NE CR 225 (From Lawtey end to Clay County line) and NE 216th St. (Both sides)

 

1 Squad will be Picking up trash on NW CR 200A and NE CR 200B

 

1 Squad will be Picking up trash & Weed eating NW CR 233