Tentative Work Schedule

July 1, 2019

 

Work in the NE section consists of Patching pot holes on NE 17th, NE 219th, NE 20th & NE 223rd and Grading NE 12th, dirt part of NE 171st, NE 5th,NE 19th and NE 21st

 

Work in the NW section consists of Zipping and Packing NW 37th Ave. 

 

Work in the SE section consists of Grading SE 38th, SE 49th, SE 86th & SE 61st., Installing culverts on SE 48th and SE CR 21B and Mowing SE CR 214 and SE CR 21B

 

Work in the SW section consists of SW 85th Lane and Cut trees out of ditch on SW CR 231 (Dedan Loop)

 

 

.We received 3 DOC Squads for a total of 15 people

 

1 Squad will be Picking up trash and Weed eating on SE 57th St. and SE 21st Ave.

 

1 Squad will be Picking up trash on SE 144th St. and SE CR 100A

 

1 Squad will be directing traffic for Installing culverts on SE 48th and SE 21B