Tentative Work Schedule

July 8, 2019

 

Work in the NE section consists of Grading NE 204th

 

Work in the NW section consists of Grading NW 41st, NW 44th, NW 219th and NW 212th St and Cleaning out the ditch on NW CR 225

 

Work in the SW section consists of Grading SW 163rd St. and Cut up, Load and Haul off downed trees and debris on SW 161st St.

 

 

We received 2 DOC Squads for a total of 9 people

 

1 Squad will be Removing trees and debris from SW 161st St.

 

1 Squad will be Picking up trash and Weed Eating on SE CR 100A