Tentative Work Schedule

 

August 6, 2018

 

Work in the NE section consists of Removing a tree from the creek on NE 15th Pl.

 

Work in the NW section consists of Limerocking NW 41st Ave., Scooping ditches on NW 219th Ter. and Brushing and Re-Grading NW 74th Ave.

 

Work in the SE section consists of Installing a culvert on SE 9th Ave. and Repairing the ditch and Patching driveways on SE 66th St.

 

 

We received 3 DOC Squads for a total of 15 people

 

1 Squad will be repairing a ditch and patching driveways on SE 66th St.

 

1 Squad will be removing a tree from the creek on NE 15th Pl.

 

1 Squad will be patching pot holes on