Tentative Work Schedule

January 11, 2022

 

Work in the NE section consists of Grading NE 171st St. and NE 12th Ave., Scoop ditch on NE 19th Ave. and Add limerock to low spots on NE 21st Lane

 

Work in the NW section consists of Grading NW 177th St. and NW 62nd Lane and Mowing ROW on Market Road, NW 36th, NW 37th and Pleasant Grove

 

Work in the SE section consists of Prepping SE 52nd St. for Spraying

 

 

We received 1 DOC (BCSO-JAIL) Officer and 3 Inmates and they will be picking up trash on SW CR 18