Work Schedule

Work in the NW section consists of Grading, Zipping a road, Scooping ditches, Chipping debris, Trimming limbs on ROW and Patching driveways

 

Work in the SW section consists of Lime rocking (2) roads

 

 

We received 3 DOC Squads for a total of 15 people

 

1 Squad will be Chipping debris in NW

 

1 Squad will be handling traffic control for scooping ditches in NW

 

1 Squad will picking up trash, weed eating and Mowing in SE

 

 

1 Squad from The Transition House (2 people) will be patching driveways