Tentative Work Schedule

September 14, 2023

 

Work in the NE section consists of Cleaning out Ditches on NE 14th Ave. and NE 264th and Mowing NE 14th Ave., NE 15th Ave., NE 16th Ave. and NE 154th with the Zero Turn

 

Work in the NW section consists of Grading NW 219th Ter., NW 74th Ave. and NW 215th Way, Mowing Shoulders of the Road on NW 185th St. and NW 59th Loop and Mowing NW CR 125, NW CR 225A and NW CR 225

 

Work in the SE section consists of Grading and Prepping SE 11th foe Chip Seal and Zipping and Grading SE 84th Ave.

 

 

We received 2 DOC (BCSO-JAIL) Officers and Inmates and they will be Weed Eating around Culverts, Signs and Mailboxes on NE 154th and NE 21st and the Intersection of NW CR 229 and NW CR 225.