Tentative Work Schedule

January 21, 2020

 

Work in the NE section consists of Clearing new road and Hauling off debris off of NE 20th Lane

 

Work in the NW section consists of Grading NW 75th Ave., NW 188th and NW 178th Loop and Patching Pot Holes on NW 45th Ave.

 

Work in the SW section consists of Shoulder work on SW CR 18

 

 

We received 1 DOC Squad for a total of 3 people and they will be directing traffic on SW CR 18 for shoulder work