Tentative Work Schedule

September 1, 2020

 

Work in the NE section consists of Grading NE 223rd St. & NE 24th Ave.

 

Work in the NW section consists of Grading NW 71st Ave. (between NW 180th and NW CR 229), Cut Shoulders on NW CR 225 and Mow NW CR 235

 

Work in the SE section consists of  Grading SE 94th St.

 

Work in the SW section consists of Cutting ROW on SW 114th St., Patching Pot Holes on SW CR 227, Mowing SW CR 235, SW 161st St., SW 151st and SW 144th and Moving a tree on SW 139th Way

 

 

We received 2 DOC Squads for a total of 10 people

 

1 Squad will be Patching Pot Holes on SW CR 227

 

1 Squad will be Weed eating the Lincoln City Park around fence, nature trail and inside playground area