September 25, 2019

 

Work in the NE section consists of Grading NE 12th, NE 171st, NE 173rd, & NE 5th, Cleaning out the ditch on NE 14th Ave. and Putting water on NE 204th,

 

Work in the NW section consists of Mowing NW 421st Ave. and Grading NW 203rd, NW 205th & NW 51st Ave. (Olin's Mobile Home Park)

 

Work in the SE section consists of Grading SE 59th Ave. and off SE CR 100A, Mowing SE CR 221, SE CR 325, SE CR 18, Behind Tony's Pizza, SE 8th Ave. and SE 35th 

 

Work in the SW section consists of Grading SW 155th St. and Crosby Lake area, Hauling off debris from creeks on SW CR 225 (3 Pipes) and SW 106th Ave, Patching troughs on SW CR 18 and Mowing SW CR 231 and SW CR 235

 

 

We received 3 DOC Squads for a total of 12 people

 

1 Squad will be Weed eating SW CR 231 (Dedan Loop)

 

1 Squad will be Hauling off debris from creeks and Patching troughs on SW CR 18

 

1 Squad will be directing traffic and assisting with the Cleaning out a ditch on NE 14th Ave.