Work Schedule

 

Work in the NW section consists of Grading, Blowing out culverts and Patching pot holes

 

Work in the SE section consists of lime rocking a road, Installing culverts, Grading a milled road and Blowing out culverts

 

Work in the SW section consists of Digging a ditch, Grading milled roads and Blowing out culverts

 

 

We received 2 DOC Squads for a total of 10 people

 

1 Squad will be assisting with traffic control for installation of culverts

 

1 Squad will be weed eating a ditch in the NW

 

 

1 Squad from The Transition House (2 people) will be patching pot holes in the NW