Tentative Work Schedule

October 13, 2020

 

Work in the SE section consists of Grading SE 44th (Odd Fellow Cemetery Road)

 

Work in the NW section consists of Grading NW 45th Ave., NW 74th and NW 215th Way and Mowing ROW on NW 75th Ave.

 

Work in the SW section consists of Grading SW 66th, Prepping SW 106th Ave. (Front part) for Fog Sealing, Trimming trees on SW CR 235, Chipping and Mulching limbs on SW CR 235, Mow SW CR 231 (Dedan Loop) and SW CR 18, Clean out ditches on SW 101st Ave. and Fix a driveway on SW CR 225

 

 

We received 1 DOC Squad for a total of 5 people and will be Chipping on SW CR 235