Tentative Work Schedule

December 4, 2018

 

Work in the NE section consists of Grading Strawberry Acres, NE 20th Lane & 205th and Mowing NE 171st St with the Side Arm

 

Work in the NW section consists of Working the milling on NW 185th and Patching driveways on NW 41st Ave.

 

Work in the SE section consists of Mowing SE 109th, 21st Ave. and SE CR 100A

 

Work in the SW section consists of Spreading 1 load of limerock on Park St. in Brooker, Grading SW 136th, 155th & 137th, Mowing with the Side Arm in City of Brooker and Patch pot holes on SW CR 235

 

 

We received 3 DOC Squads for a total of 16 people

 

1 Squad will be Patching driveways on NW 41st Ave.

 

1 Squad will be patching pot holes on SW CR 235

 

1 Squad will be working around the Shop cleaning up