Tentative Work Schedule

August 23, 2018

 

Work in the NE section  consists of Grading NE 171 St. (a milled road)

 

Work in the NW section consists of Pulling ditches on NW 257th, Moving equipment to and Pulling Ditches on NW 188th St., Packing NW 71st, Scooping the ditch on NW 53rd Ave., Grading NW 38th Ave. and Patching 2 driveways at 3114 NW CR 225

 

Work in the SE section consists of Grading SE 49th Ave., SE 33rd, SE 87th, SE 89th, SE 16th, SE 94th and Crystal Lake Homesites area, Scooping the ditch at 14426 SE CR 100A and Mowing SE CR 214, roads in Keystone Golf and Country Club and Seminole Ridge area

 

 

We received 3 DOC Squads for a total of 17 people

 

1 Squad will be with Marvin patching 2 driveways at 3114 NW CR 225

 

1 Squad will be weed eating in Conerly Estates

 

1 Squad will be performing traffic control Scooping a ditch at 14426 SE CR 100A and installing a culvert on NW CR 235