Tentative Work Schedule

March 11, 2020

 

Work in the NE section consists of Spraying NE 204th with Fog Seal

 

Work in the NW section consists of Fog Sealing NW 219th St., Grading NW 38th Ave. & NW 182nd St., Patching Pot Holes on NW 177th St. and Building a pad at the Heilbronn Springs Fire Department

 

Work in he SW section consists of Patching Pot Holes on SW CR 235 and Mowing SW CR 225A and SW CR 18

 

 

We received 2 DOC Squads for a total of 8 people

 

1 Squad will be assisting with Patching Pot Holes on SW CR 235 and NW 177th St.

 

1 Squad will be directing traffic on NW 219th St.