Tentative Work Schedule

January 2, 2019

 

Work  in the NE section  consists of Mowing NE 17th Ave., NE 20th Ave., NE 213th & NE 219th and Patching pot holes and driveways on NE 17th Ave.

 

Work in the NW section consists of Grading NW 25th, NW 238th, NW 251st, NW 267th, NW 261st & NW 63rd Ave. and Grade NW 177th, NW 62nd, NW 38th, NW 219th, NE 219th & NW 182nd

 

Work in the SE section consists of Grading SE 21st Ave., SE 140th, SE 134th, SE 125th Ter. & SE 129th

 

Work in the SW section consists of Grading SW 155th Ave., SW 136th St., SW 160th, SW 168th, SW 144th & SW 137th

 

 

We received 3 DOC Squads with a total of 17 people

 

1 Squad will be Patching pot holes & driveways on NE 17th Ave.

 

1 Squad will be picking up trash and weed eating on NW CR 125

 

1 Squad will be picking up trash and weed eating on NW CR 225A and NW 27th Ave.