Work in the NW section consists of Grading NW 53rd Ave. and NW 219th St., Shoulder work on NW CR 225 and Mow NW CR 225 with Zero Turns

 

Work in the SE section consists of Prepping SE 46th Ave., Mow SE 21st Ave. and all roads off of it and Patch SE 30th St.

 

Work in the SW section consists of Cleaning out ditches on SW 66th Ave.

 

 

We did not receive any DOC Squads today