Tentative Work Schedule

September 10, 2020

 

Work in the NE section consists of Trimming ROW on NE 219th St.

 

Work in the SE section consists of Grading SE 46th Loop

 

Work in the NW section consists of Grading NW 219th St & Picking up and Hauling off dirt from ditch on NW 71st Ave.

 

Work in the SW section consists of Grading SW 85th Lane and SW 101st Ave., Mowing SW CR 227, SW CR 225 & SW CR 18, Fixing a culvert on SW CR 225A and SW CR 18

 

 

We received 2 DOC Squads for a total of 10 people

 

1 Squad will be Cleaning out Pratt St. Pond

 

1 Squad will be Weed eating Big Bridge and Guardrails on SW CR 18 near Riverbend Estates