Tentative Work Schedule

March 15, 2021

 

Work in the NE section consists of Cleaning out ditches on NE 10th Ave.

 

Work in the NW section consists of Mowing ROW on NW 132nd Pl

 

Work in the SE section consists of Grading SE 49th, 41st, 43rd, 101st & 46th and Mowing SE CR 18

 

Work in the SW section consists of Grading SW 132nd Ave., Cleaning out ditches, Blowing out ditches and Mowing on SW CR 231 (Dedan Loop) and Mowing SW CR 18

 

 

We received 2 DOC Squads for a total of 10 people

 

1 Squad will be Finishing Concrete Slab work at Sampson Lake Boat Ramp and Picking up trash and weed eating on NW CR 225 from SR 16 to 301

 

1 Squad will be assisting with Traffic Control for Cleaning out ditches on SW CR 231 (Dedan Loop)