Tentative Work Schedule

August 15, 2019

 

Work in the NE section Grading NE 20th Ln., NE 204th St., NE 171st, NE 12th, NE 173rd & NE 19th

 

Work in the NW section consists of Installing a culvert on NW CR 225 and Mowing NW 62nd Ave., NW 214th St., NW CR 229A, NW 216th St. & NW CR 200A

 

Work in the SE section consists of Removing trees on SE CR 18 and Patching Pot Holes SE 35th St. & SE 30th St.

 

Work in the SW section consists of Grading SW 101st Ave., Removing trees on SW CR 235 near SW 136th Ave. & SW 132nd and Mowing SW CR 18

 

 

We received 3 DOC Squads for a total of 15 people

 

1 Squad will be Cutting up trees on SW R 235

 

1 Squad will be working at the Shop

 

1 Squad will be directing traffic for installing a culvert on NW CR 225