Tentative Work Schedule

April 5, 2023

 

Work in the NE section consists of Moving Equipment to NE 17th Ave. and Prepping for Milling tomorrow

 

Work in the NW section consists of Grading NW 237th St., NW 209th St., NW 35th Ave. and NW 38th Ave.

 

Work in the SW section consists of Patching Shoulders on SW CR 235 and Mowing SW CR 231 (Dedan Loop) and SW CR 18

 

 

We received 1 DOC Officer (BCSO-JAIL) and 3 Inmates and they will be Picking up Trash on SW 101st Ave.